Orchard Storage – Project Timeline
Key milestones and upcoming public meetings
Town Staff Review Completed
May 20, 2025
Planning, Engineering, Fire, and Landscape departments issued initial comments.
Zoning Application Filing
Target – Mid July 2025*
We plan to submit the full Planned Development package to the Town.
Environmental Commission Hearing
Tentative – Early August 2025*
Public meeting focusing on trees, drainage, and open-space requirements.
Planning & Zoning Hearing
Anticipated – Late September 2025*
First public hearing to review the site, architecture, and community feedback.
Town Council Vote
Projected – Early October 2025*
Final zoning decision, subject to Town scheduling.
Permits & Groundbreaking
Earliest – Winter 2025-26*
Construction will start once detailed plans are approved and zoning is in place.
Stay Informed
Sign up for email updates about meeting dates and construction progress.